Cost Estimate Without Quantity Structure: Process Flow
You can create a cost estimate without quantity structure for a material that does not yet have a PP quantity structure. For such materials, you create a quantity structure using a unit cost estimate.
You can also use existing data for material cost estimates without quantity structure, data such as materials, internal activities, work centers, and material cost estimates.
You have checked the settings in the costing variant. For more information, see Preparation for Material Costing.
You create a material cost estimate without quantity structure based on a costing variant.
For more information, see Creating a Cost Estimate Without Quantity Structure.
You enter the costing data manually using the unit cost estimate.
For more information, see:
Note
As an alternative to single-level unit costing, you can edit the cost estimate without quantity structure on a multilevel basis. For more information, see Multilevel Unit Costing.
The system determines the prices for materials and internal activities as well as overhead and process costs.
For more information, see:
You analyze the results and save the cost estimate.
For more information, see:
You can update the material master record with the costing results, and transfer the costing results to Profitability Analysis
.
For more information, see:
You can archive and delete material cost estimates.
For more information, see: